Tuesday, August 26, 2008
Footings Progress
The City inspector and the ACC has verified the compliance for the footings. The footings will be poured today and then the slab will be formed, graded and ready for the underground work to begin.
Monday, August 25, 2008
Friday, August 22, 2008
Off and Rolling!
The lot has been graded, the home and lot area has been staked and the footings are half dug, the temporary power pole has been set and inspected and now has power, the water metor has also been installed and is active.
Wednesday, August 13, 2008
Permit Issued!
The City of St. George has issued the building permit for this wonderful home. We now have all of the official approvals to begin construction.
Monday, August 4, 2008
Building Permit Application at City
The plan and the building permit application has been submitted to the City of St. George and is currently under review.
Subscribe to:
Comments (Atom)