Wednesday, February 11, 2009
Home Completed!
This home has been completed on schedule and has turned out to be "a work of art." This home has become even better than imagined. With incredible detail and design it compliments the beautiful scenery that surrounds the home.
Thursday, November 20, 2008
Drywall Progress
The drywall is hung and taped and the walls are going to be plastered and textured next.
Friday, November 7, 2008
Home Update
The framing is completed along with the rough plumbing, mechanical, gas and electrical. The insulation is currently being installed and the drywall company will begin hanging the sheetrock early next week.
Friday, September 19, 2008
Monday, September 15, 2008
Lining out for framing
Preparation for framing has begun. The home is being lined out. The trusses are ordered and the windows are to be ordered today.
Wednesday, September 10, 2008
Slab Poured
This morning at 3:00 AM we poured the main slabs cement. The pour went very smooth. The Garage and Theater room slabs will be poured this week.
Thursday, September 4, 2008
Slab Prep
The exterior footings have been poured and the slab is being prepped and the stem wall for the sunken theater room is being done.